Exploration plans are intended to cover early exploration activities that are generally expected to have minimal to low on-the-ground impact. Activities that require an exploration plan include:
- Ground geophysical surveys that require a power generator;
- Line cutting that is a width of 1.5m or less;
- Mechanized stripping of a total surface area of less than 100m², within a 200m radius;
- Pitting and trenching of bedrock material 1m³ up to 3m³ in volume, within a 200m radius; and
- Mechanized drilling where the drill is less than 150kg (total weight not including rods/casing).
Submitting an Exploration Plan
A mining lands holder or authorized agent can submit an exploration plan by selecting “Submit Plan/Permit for Early Exploration Activities” from the Early Exploration Activities tab in MLAS.
Please refer to the MNDM directives for instructions for how to submit Exploration Plans in MLAS, and to the Mining Act, its regulations, policies, and How To Guides for more information.
When an exploration plan is submitted:
The proponent will...
MNDM will...
- Identify and notify the appropriate Aboriginal communities whose Aboriginal and/or treaty rights have the potential to be adversely affected by the proposed exploration activities, and respond as appropriate to concerns they may raise; and
- Post the exploration plan to the Ministry website which can be accessed by the general public seeking information about proposed early exploration activities.